NEW QUESTION # 46
What PPIDS master data is necessary for using PP/DS? Note: There are 2 correct answers to this question
- A. Location
- B. Resource
- C. Material
- D. Production version
Answer: C,D
NEW QUESTION # 47
Project Structure
Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times. Therefore they want to get an overviews of the budget updates.
What standard report do you recommend?
- A. Line item report for budget
- B. Structure overviews for budget.
- C. Hierarchical report on budget updates.
- D. Cost element report on budget updates.
Answer: C
NEW QUESTION # 48
Cost & budget
A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget.
What action do you have tsolve the problem?
- A. Activate availability control for the important WBS element. Define the tolerance limit on each WBS element.
- B. Activate availability control For projects in the control area. Enter the plan data for each WBS element.
- C. Activate availability control in the assign budget profile. Defined the tolerance limit in the customizing.
- D. Activate commitment
- E. management in the project definition. Enter the budget in the master data of the top WBS element.
Answer: C
NEW QUESTION # 49
You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use?
- A. Detailed planning for WBS
- B. Easy Cost Planning (ECP) for WBS
- C. Planning of overall values
- D. Unit costing for WBS
Answer: C
NEW QUESTION # 50
The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.
- A. Company code
- B. Planning department
- C. Plant
- D. Controlling area
Answer: D
Explanation:
"The controlling area that you specify when you create a project definition is unique for the entire project. You specify the controlling area just once when you create the project." Reference: 2
NEW QUESTION # 51
Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.
- A. You can also represent a project using a WBS and one or more networks.
- B. You can create a project based on a Activity.
- C. You cannot use the characteristics of both the structures (WBS and Networks) together to represent a project.
- D. You can map a project using only one WBS or one network.
Answer: A,B
Explanation:
You can use both WBS and networks to represent a project in SAP S/4HANA Project System. A WBS shows the hierarchical structure of the project, while a network shows the flow and dependencies of the project activities." According to SAP Blogs3, "You can create a project based on an activity by using the app 'Create Project from Activity'." Reference: 13
NEW QUESTION # 52
Resources
How can you define external task in your project.
Note : there are 2 correct answers for this question.
- A. Create an external activity in a network.
- B. Create a service activity in a network.
- C. Assign a purchase order for external processing to the project definition.
- D. Create a service milestone.
Answer: A,B
NEW QUESTION # 53
Revenues & Payment
Your customer wants to plans and post revenues for WBS elements.
What is crucial for the implementation of revenues planning and posting for WBS elements?.
- A. A sales order item has to be assigned to each WBS element used for revenue planning.
- B. The indicator "Project type" must be set to "Customer project".
- C. Revenue planning and billing must be activated in the corresponding network type.
- D. At least one WBS element must be a billing element.
Answer: A
Explanation:
Revenue planning and posting for WBS elements is a function that allows you to plan and record revenues for customer projects. The crucial prerequisite for this function is that a sales order item has to be assigned to each WBS element used for revenue planning. The sales order item serves as a reference object for revenue recognition and billing. You can assign a sales order item to a WBS element in the Billing Plan tab of the WBS element master data. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002
NEW QUESTION # 54
Cost and budget
A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do not want to produce..
Which setup do you recommend?
- A. Assign a sales order to a project with appropriate hierarchy levels.
- B. Assign Several production orders to a sales order
- C. Assign One production order to a sales order
- D. Assign a network to a sales order
Answer: A
Explanation:
To avoid unnecessary stock cost, you can assign a sales order to a project with appropriate hierarchy levels. This means that you can create a project structure that matches the multilevel production environment with bill of material and routing. You can assign a sales order item to a WBS element that represents the finished product and assign production orders to WBS elements that represent the semi-finished products. This way, you can use project stock to manage the materials required for the project and avoid creating inventory for intermediate products. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002
NEW QUESTION # 55
To which object can you assign a factory calendar?
- A. Network header
- B. Material component
- C. Milestone
- D. Relationship
Answer: A
Explanation:
To assign a factory calendar, you can use the network header. The network header is a structural element of a network that contains general data and settings for a network, such as its order type, number range, scheduling parameters, and so on. The network header also contains the factory calendar field, which allows you to assign a factory calendar to a network. A factory calendar is a parameter that defines the working days and holidays for a plant or a location. A factory calendar is used to determine the dates and durations of activities and networks based on their workdays and non-workdays. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 56
A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question
- A. Cost element reports
- B. Resource reports
- C. Hierarchical reports
- D. Structure information system reports
Answer: B,C
Explanation:
Resource reports and hierarchical reports are some of the possible reports that you can use to analyze the capacity requirements of your network activities. Resource reports display capacity requirements and availability for work centers or resources over a period of time. Hierarchical reports display capacity requirements and availability for work centers or resources in a hierarchical structure, such as plant, MRP controller, or work center group. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 57
Material
Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement scheduling of events.
What is the requisites for implement scheduling of events?
- A. Priority of events must be set.
- B. Events must be released manually.
- C. Event scenarios must be defined.
- D. Scheduling parameters for material scheduling must be set.
Answer: C
NEW QUESTION # 58
Resources
How can you define external task in your project.
Note : there are 2 correct answers for this question.
- A. Create an external activity in a network.
- B. Create a service activity in a network.
- C. Assign a purchase order for external processing to the project definition.
- D. Create a service milestone.
Answer: A,B
Explanation:
"You can create external activities in a network to represent tasks that are performed by external service providers or vendors." According to SAP Press4, "You can create service activities in a network to represent tasks that are performed by internal service providers." Reference: 4
NEW QUESTION # 59
Which statement is valid regarding networks? Note: There are 2 correct Answers to this question.
- A. A network activity can be assigned to several WBS elements.
- B. A network can be activity-account-assigned and header-account-assigned.
- C. Relationships can be used to connect activities of different networks.
- D. Material components can be assigned to activity elements.
Answer: B,C
NEW QUESTION # 60
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question
- A. The Project Stock indicator is set in the project definition (non-valuated or valuated)
- B. A procurement indicator must be assigned to the activity
- C. The material master of the component must permit project stock management
- D. The network activity is assigned to a WBS element
- E. The network is assigned to a sales order item
Answer: A,C,D
NEW QUESTION # 61
Cost & Budget.
A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?
- A. Settlement rules
- B. Investment profile.
- C. Costing Sheet
- D. Results analysis key
Answer: A
NEW QUESTION # 62
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question
- A. A bill of material with sales views
- B. Assignment between material and standard network
- C. A material master with sales views
- D. A production order
- E. Standard network with activities
Answer: B,C,E
Explanation:
According to SAP Press2, "To use assembly processing, you need a material master with sales views, a bill of material (BOM) for the material, a standard network with activities, and an assignment between the material and the standard network." Reference: 2
NEW QUESTION # 63
Dates
How are earliest dates and latest dates of activities schedule?
- A. Earliest dates are scheduled by backward scheduling, and the latest dates by forward scheduling.
- B. Earliest dates are scheduled by backward scheduling, and the lates dates by copying the earliest dates.
- C. Earliest dates and latest dates are scheduled by forward scheduling.
- D. Earliest dates are scheduled by forward scheduling , and the latest dates by backward scheduling.
Answer: D
NEW QUESTION # 64
How can you update the degree of processing for an activity?
- A. By confirming the activity
- B. By using results analysis
- C. By scheduling the activity
- D. By changing the activity
Answer: A
Explanation:
To update the degree of processing for an activity, you have to confirm the activity. Confirming an activity is an action that records the actual data for an activity, such as actual start and finish dates, actual work and costs, and actual degree of processing. The degree of processing is a percentage value that indicates how much of an activity has been completed. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 65
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
- A. Project profile
- B. Network type
- C. Data entry profile
- D. Network profile
Answer: C
Explanation:
To set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing, you use the data entry profile as an influencing field. CATS is a tool that allows you to record working times and tasks for project activities. The data entry profile is a parameter that defines the layout and functions of the CATS user interface. You can use the data entry profile to determine which fields are displayed or hidden, mandatory or optional, modifiable or read-only, and so on. Reference: https://help.sap.com/doc/saphelp_scm700_ehp02/7.0.2/en-US/69/f3055130534338e10000000a154ce5/content.htm
NEW QUESTION # 66
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.
- A. The Project Stock indicator is set in the project definition (non-valuated or valuated).
- B. The network activity is assigned to a WBS element.
- C. The network is assigned to a sales order item.
- D. A procurement indicator must be assigned to the activity.
- E. The material master of the component must permit project stock management.
Answer: A,D,E
NEW QUESTION # 67
......